in Company news, News

DOPPLER lifts are manufactured to handle and adjust to special needs, without losing their uniqueness. That’s why Keighley Lifts UK Ltd. chose and assigned this great project to DOPPLER!

The Managing Director of Keighley Lifts UK Ltd, Mr. Stuart Boocock and his partners Mr. Garry Boocock and Mr. Justin MacGregor worked faultlessly to bring the project in time. Following, they describe us the whole project presenting all the details…

The Roach Road Project was completed early this year in the prestigious area of Stratford, in the central London that hosted the Olympic Village and the Olympic Stadium. Once the London 2012 Summer Olympics was over, it was decided to revitalize the area where once stood the Olympic village in order to make exclusive and modern apartments for the ever growing population of central London.

This project required the installation of two DOPPLER lifts with these features

• Type of lifts: ECO lli Traction, Passenger, Fire fighting lifts
• Capacity: 630kg
• No of passengers: 8
• No of stops: 6
• Car speed: 1.6 m/s
• Travel: 21075mm

The work schedule was strict and we had 10 weeks to install both DOPPLER lifts and do the necessary tests. DOPPLER delivered the lifts in 4 weeks and we managed to complete the project within the time frame. The lifts were put into operation successfully before the first residents moved into the luxury apartments.

This remarkable project was another great success and we are now proceeding to our 9th year of cooperation with DOPPLER!’